>> commissioner ransom-scott: mr. chair, no questions. mr. brandon, thank you so much for the presentation and the work that you've done towards this project. i don't have any questions at this moment. thanks a lot. >> chair bustos: thank you. vice chair rosales? any questions or comments? >> vice chair rosales: i didn't have any initial questions, but i guess the only question that pops up on the presentation is regarding the estimated timing of next steps. is this the -- is the schedule that we have here that you've presented to us the same schedule that was envisioned on the project? >> no, commissioner. we have been delayed. so as i said earlier, in 2018, we did complete a schematic design for the project. and at that point we were hoping to bring that before the commission for its approval, but at the same time as i was working on overseeing that schematic design, we were also working on the draft operations budget. so we presented both the budget in conjunction with the design to the tjpa for its review at this time. when they realized